Skip to content
OrderDiff

Meridian Components (sample) — order audit

A sample report, built from invented orders.

Sample data. These orders and suppliers are invented, so the figures below are illustrative — but the arithmetic, the tolerances and the wording are exactly what a real batch produces.

Total at risk

€5,978

€5,978 at risk, deliveries up to 28 days later than ordered, across 16 orders. 5 of them differed from what you agreed.

Net change to what you will be invoiced: +€3,903

16 orders compared5 with changes11 clean1 file not compared2026-01-14 to 2026-03-02

What changed

ChangeOrdersOccurrencesAt riskInvoice change
Price increased22€4,940+€4,940
Short-shipped11€637.50-€637.50
Line dropped11€400.00-€400.00
Delivery delayed2228 days—
Line split across deliveries11——

By supplier

SupplierOrdersWith changesClean rateAt riskInvoice change
Northgate Industrial6267%€5,558+€4,283
Westmill Supply5260%€400.00-€400.00
Alpine Fasteners11—€20.00+€20.00
Kessler Bearings40———

The 5 worst orders

With the findings behind each, so every figure above can be checked against your own records.

PO-2026-1041Northgate Industrial2026-01-14
€4,920 at riskinvoice +€4,920
  • Line 10 / NG-4410: unit price rose from EUR 128.50 to EUR 149.00 per EA (15.95%). Costs EUR 4,920.00 across 240 EA.
  • Line 10 / NG-4410: delivery slips by 23 days, from 2026-02-16 to 2026-03-11.
PO-2026-1077Northgate Industrial2026-01-22
€637.50 at riskinvoice -€637.50
  • Line 10 / NG-2200: ordered 1000 EA, confirmed 850 EA — short by 150 EA (15%). That is EUR 637.50 of ordered goods the supplier has not committed to.
PO-2026-1160Westmill Supply2026-02-11
€400.00 at riskinvoice -€400.00
  • The supplier explicitly declined this line. This is a stated refusal, not an omission: Line 20 / WM-1020 will not be supplied. EUR 400.00 is at stake.
PO-2026-1201Alpine Fasteners2026-02-20
€20.00 at riskinvoice +€20.00
  • Line 10 / AF-8800: unit price rose from EUR 0.42 to EUR 0.44 per EA (4.76%). Costs EUR 20.00 across 1000 EA.
PO-2026-1112Westmill Supply2026-02-03
28 days late
  • Line 10 / WM-5500: delivery slips by 28 days, from 2026-04-10 to 2026-05-08. This is the last of 3 split deliveries.
  • Line 10 / WM-5500 was split across 3 confirmation lines. Quantities are compared as a total, and the delivery date is taken from the last part.

How this was produced

  • Every confirmation was compared against its purchase order line by line: quantity, unit price, delivery date, unit of measure and currency.
  • The comparison is deterministic. The same two documents always produce the same result, and no figure here is estimated.
  • Value impact is the money each change costs or saves, computed from the documents themselves. A change with no derivable figure — a delivery delay, for instance — is counted but not priced, and shown as a dash rather than as zero.
  • 1 uploaded file was not compared, because it could not be paired with a counterpart. Nothing above accounts for it.

Run this on your own orders

Upload a quarter of purchase orders and confirmations and get the same report for your own suppliers. No account needed.

Run a free audit